Total GFA |
172,902.5m² |
Total Height |
Main Tower:242.1m;Podium:23.25m |
Stories |
60Stories:57 stories above ground 3 stories underground |
Office Floor |
6/F to 38/F |
Typical Floor Plate |
Approx.1,974m² |
Description Of Standard Floor |
Approx.11.4m |
Electrical System |
Two transformer substations--Xinjiekou transformer substation and Changjiang Road transformer substation supply 4 loop-designed power supply |
HVAC System |
Low Area:fan-cooled,fresh air system |
|
High Area:Intermational Standard VAV (variable air volume air) Conditioning System |
Elevator |
14 High-speed Passenger Elevators,2 Service Elevators(Office Floors) |
Window Features |
Tower Building:Aluminum curtain wall/window treatment which has double-sided |
|
Podium Building:Utilizing stone and glass with 3D & 6D adjustable unit curtain wall. |
Parking Space |
550 lots |
Estimated Completion Time |
The Ending of 2013 |